From time management to schedule management: the new time management in a project

time-management-1

Schedule management or project scheduling is the process of project time management through milestones, activities and final results, usually indicating the expected start and end dates.

A schedule or scheduling is the project or program calendar.

This shows how the work will progress over a period of time and takes into account factors such as limited resources and the uncertainty estimation.

This process begins with the work necessary to meet the requirements of the stakeholders.

This includes the technical / practical work that creates the results and the management activity that deals with aspects such as risk management and stakeholder management.

Definition of types of work

Some types of work can be defined much more easily than other types.

Engineering work, for example, tends to have detailed and complete specifications from the start, while some IT activities follow a more iterative approach to define what needs to be done.

The approaches to time calculation must be equally flexible.

In some cases, you can use rigorous techniques to model the work and calculate the detailed times.

In other cases, general estimates have to be made from the start, then, as the project continues, they are constantly refined thanks to the information available.

A detailed model can be used to perform “what-if” calculations and analysis to test the result of potential events.

For example: “what happens if the X resource is not available in February?” Or “what happens if there are unfavorable weather conditions in March?”.

Rolling Wave Planning

The detailed high-level planning approaches usually follow the so-called  “rolling wave” planning.

Short-term work is generally better defined and can be subject to more rigorous and comprehensive planning.

Long-term work is more vague and subject to changes and will be detailed working progress.

The detail window then moves along the program like a “rolling wave”, literally a rolling wave.

The most commonly used graphic planning form is the Gantt chart.

In its simplest form it uses bars on a horizontal chronological scale to show the beginning, duration and end of the various activities.

Variants of the Gantt chart can transmit all types of information adapting to the circumstances.

At the end of the work scheduling shows what has been planned and what really happened and can be an important tool in identifying and determining the lessons learned.

How to perform project scheduling

Before deepening  project planning, let’s examine the basics.

You have to ask yourself three questions to start project planning:

  1. What must be done?
  2. By when will it be done?
  3. Who will do it?

time-management-to do list

Once you have the answers to these questions, you can start planning dates, linking activities, setting duration, milestones, and resources.

Following are the necessary steps  to plan a project:

  • Define activities: Using a Work Breakdown Structure (WBS) structure and a deliverable diagram, you can begin to perform these tasks and organize them by mapping the activities needed to complete them in an order compared to what is necessary;
  • Making estimates: Once the activities have been defined and divided, it is necessary to determine the time and effort required to complete them;
  • Determine dependencies: Tasks are not isolated and often it isn’t possible to start a new one until the previous is not completed. This is the so-called dependence of activities;
  • Assign resources: The last step to finalizing the planned program is to decide which resources will be needed to perform these tasks on time.

You will have to choose the project team and the time of the collaborators will have to be planned exactly following the planned activities in the planning.

As the complexity of work increases, it becomes impractical to maintain a single detailed program.

Large-scale projects will often use wave planning in which only short-term work is shown in detail with the long-term work that is shown in summary.

As the amount of management activity increases, it may be useful to create separate delivery plans for different areas such as a communication plan, a technical plan, a marketing plan, etc.

The need for multiple plans is inevitable as the complexity of project increases.

To be effective, the project manager must ensure that similar programming policies are adopted throughout the program.

These policies can be defined in a planning management plan.

The scheduling management plan has essentially three parts:

  • Development planning
  • Control
  • Planning of changes

Development planning

In this section the procedures for the development and revision of the program are established.

The personnel responsible for the development is identified and the potential contribution of the project team members is discussed.

Written procedures for estimating asset duration and budgets, contingency levels, and resources are specified for the project.

Moreover, if the project is complex, a project planning software is very often a useful tool to have.

Scheduling check

In this section the procedures for measuring and monitoring the project program are implemented.

Throughout the project, planning deviations and costs should be known or calculated regularly, which requires an estimate of the percentage of completion of each activity according to scheduling.

At this stage it is necessary to have clear answers to the following questions:

  • How will the program be measured?
  • Which units will be used to measure completeness of activities?
  • Who will measure it?
  • How often will it be measured?

Scheduling changes

Normally, any change to the initial project planning must be communicated and approved.

In fact, in most cases, someone has initially approved the project budget and deadline and expects to receive results accordingly.

That person is usually called the “project sponsor“.

And it is the project sponsor together, often, to the stakeholders who must be informed and approve all the changes to the initial planning.

time-management-desktop

                                                                                                                                         Thanks for the image to  Watch List

Here are the basic questions to consider in this case:

  • What are the appropriate reasons for a change of program?
  • How much notice do you need?
  • Who must approve the changes?

Project planning is probably one of the most difficult jobs of a project manager, but the coordination of delivery dates on estimates can be simplified and made more efficient when you have gained experience and when using appropriate software management.

What are your experiences with project scheduling? Write us your comment here.

Start planning your projects.

Related Posts