A new Twproject release is out with some great features included in all plans. This is a free upgrade for all Twproject users and includes some database changes so do a complete backup before update.
If you are updating from a version before 6.3 remember to check the upgrade guide here:
https://twproject.com/support/twproject-advanced-usage/installation/update-twproject-6-3/
Gantt PDF export
The first and more important one is the new Gantt print functionality that generates a pdf with the entire Gantt finally solving the big images print browser issue.
The print button has been reintroduced in the Gantt editor to generate the pdf:
Resource operating hours
A great new feature introduced in 6.4.64001 is the resource operating hours available in the work settings tab. Thanks to this new functionality you can specify resource working hours day by day. Operating hours are considered in operator load and plan for every day load calculation.
Project progress calculation
Twproject includes now nine different automatic rules to calculate task progress.
By worklog / estimated: task progress is calculated according to the work inserted on the estimated one.
By sub-tasks (weighted): in this case Twproject considers the relevance of each sub-tasks and its progress to calculate the parent progress.
By sub-tasks completed: in this case the parent progress follow the status of its children, for example if the half of its children are closed the progress is at 50%.
By issues closed / total: project progress increase according to the number of its closed issue.
By cost / estimated & by cost / budget: Project progress increase according to costs bear in relation with estimated ones or budget.
By date: Project progress increase with end date approaching.
Different sub-tasks calculate their progress using a different rule.
You can check the complete list of new features and fixes on our change log here.