{"id":14035,"date":"2020-11-11T07:00:12","date_gmt":"2020-11-11T07:00:12","guid":{"rendered":"https:\/\/twproject.com\/?p=14035"},"modified":"2020-11-11T23:00:03","modified_gmt":"2020-11-11T23:00:03","slug":"effort-e-durata-differenza-e-priorita","status":"publish","type":"post","link":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/","title":{"rendered":"Effort e durata: differenza e priorit\u00e0"},"content":{"rendered":"<p>La stima dell\u2019<strong>effort <\/strong>e della <strong>durata<\/strong> del progetto \u00e8 una funzione chiave di qualsiasi <a href=\"https:\/\/twproject.com\/it\/blog\/il-piano-di-consegna-dei-deliverables-di-progetto\/\" target=\"_blank\" rel=\"noopener\">pianificazione di progetto<\/a>.<\/p>\n<div class=\"table-of-content\">\n<h5>INDICE DEI CONTENUTI<\/h5>\n<ul>\n<li><a href=\"#cosa\">Cosa significa effort?<\/a><\/li>\n<li><a href=\"#tempo\">Non solo Effort ma anche il fattore tempo<\/a><\/li>\n<li><a href=\"#significa\">Cosa significa durata?<\/a><\/li>\n<li><a href=\"#relazione\">La relazione fra effort e durata<\/a><\/li>\n<li><a href=\"#esempio\">Esempio di sforzo e durata del progetto<\/a><\/li>\n<li><a href=\"#durata\">Durata<\/a><\/li>\n<li><a href=\"#effort\">Effort<\/a><\/li>\n<li><a href=\"#sforzo\">Relazione tra sforzo del progetto e durata<\/a><\/li>\n<li><a href=\"#conclusioni\">Conclusioni<\/a><\/li>\n<\/ul>\n<\/div>\n<p>Lo scopo di un&#8217;efficace gestione del progetto \u00e8 portare a termine il progetto nei tempi previsti. L&#8217;accuratezza del programma di progetto complessivo dipende quindi dalla precisione delle stime di <strong>effort e durata<\/strong>.<br \/>\n<a name=\"cosa\"><\/a><\/p>\n<h2>Cosa significa effort?<\/h2>\n<p><strong>L\u2019effort si riferisce alla quantit\u00e0 di sforzo<\/strong> o alla <strong>quantit\u00e0 di lavoro svolto per completare una determinata attivit\u00e0<\/strong>.<\/p>\n<p>L\u2019effort \u00e8 denominato anche come &#8220;sforzo&#8221; ed \u00e8 definito come la quantit\u00e0 di lavoro, o il numero di unit\u00e0 di lavoro utilizzate per completare l&#8217;attivit\u00e0.<\/p>\n<p>In parole semplici, <strong>l\u2019effort \u00e8<\/strong> semplicemente <strong>il numero di ore che i lavoratori impiegano<\/strong>, concentrati su un particolare compito, <strong>per ottenere un determinato output<\/strong>.<\/p>\n<p><strong>L\u2019effort<\/strong> \u00e8 spesso espresso in ore, giorni o settimane impiegate dai lavoratori.<\/p>\n<p><a href=\"https:\/\/twproject.com\/it\/blog\/gli-stakeholders-di-progetto\/\" target=\"_blank\" rel=\"noopener\">Gli stakeholder<\/a>\u00a0spesso vogliono sapere quanto coster\u00e0 un progetto. Questo dipende principalmente dalla misura del tempo che i membri del progetto spendono per il progetto.<\/p>\n<p>Ecco quindi un semplice esempio per spiegare questo concetto:<\/p>\n<p>Per dipingere una casa sono necessarie 6 ore al giorno di lavoro per 9 giorni.\u00a0 L\u2019effort, o lo sforzo, \u00e8 quindi la quantit\u00e0 di tempo che si impiega in un giorno moltiplicato per il numero di giorni di lavoro necessari, in questo caso 54 ore. L\u2019effort \u00e8 quindi di 54 ore.<br \/>\n<a name=\"tempo\"><\/a><\/p>\n<h2>Non solo Effort ma anche il fattore tempo<\/h2>\n<p>Il tempo \u00e8 una risorsa unica, non rinnovabile e insostituibile. La stima e la <a href=\"https:\/\/twproject.com\/it\/blog\/time-management\/\" target=\"_blank\" rel=\"noopener\">gestione del tempo<\/a>\u00a0possono quindi creare o distruggere un progetto. E\u2019 di fondamentale importanza che il project manager sappia come approcciarli.<\/p>\n<p>\u00c8 importante stimare il tempo correttamente, per due motivi principali:<\/p>\n<ul>\n<li>Le scadenze per la pianificazione e la consegna del progetto derivano dalla durata stimata. Una stima inadeguata si traduce in tempi di consegna che vanno oltre le tempistiche previste e che possono non solo influire sul risultato economico dell&#8217;azienda, ma possono anche suscitare dubbi sulla competenza e affidabilit\u00e0 del project manager.<\/li>\n<li>Le scadenze regolano anche i prezzi dei contratti che, se non rispettate, possono influire sulla redditivit\u00e0 del progetto.<\/li>\n<\/ul>\n<p>Spesso per\u00f2 pu\u00f2 essere difficile capire la profonda differenza tra effort e durata. Vediamo quindi di fare chiarezza.<br \/>\n<a name=\"significa\"><\/a><\/p>\n<h2>Cosa significa durata?<\/h2>\n<p>La durata \u00e8 il tempo di calendario richiesto per eseguire qualsiasi attivit\u00e0 specifica.<\/p>\n<p>La durata \u00e8 misurata in ore, giorni, settimane, mesi o anni e pu\u00f2 essere calcolata solo dopo aver determinato che tipo e quante risorse andranno ad eseguire l&#8217;attivit\u00e0.<\/p>\n<p>La durata \u00e8 definita come l&#8217;intero tempo impiegato per completare una determinata attivit\u00e0, in base alle risorse assegnate al progetto.<\/p>\n<p>Viene misurata nello specifico da quando l&#8217;attivit\u00e0 ha inizio al giorno in cui l\u2019attivit\u00e0 termina definitivamente. Non include il tempo libero delle risorse come vacanze o altri giorni non lavorativi.<\/p>\n<p>Prendendo lo stesso esempio usato nel caso dell\u2019effort &#8211; dipingere una casa &#8211; in cui si lavora 6 ore al giorno per 3 giorni, la durata per questa attivit\u00e0 sar\u00e0 quindi di 3 giorni.<br \/>\n<a name=\"relazione\"><\/a><\/p>\n<h2>La relazione fra effort e durata<\/h2>\n<p>Solo una volta che si ha una <strong>stima dell\u2019effort<\/strong>, \u00e8 possibile <strong>stimare la durata<\/strong>.<\/p>\n<p>Questo \u00e8 strettamente correlato alla costruzione di un abbozzo di programma e <strong>implica la decisione su quante persone e risorse verranno inserite nel progetto<\/strong>.<\/p>\n<p>L&#8217;organico pu\u00f2, in una certa misura, essere cambiato durante il ciclo di vita del progetto, ma \u00e8 necessario ricordare che <strong>esiste una durata minima necessaria per alcune attivit\u00e0<\/strong>. Ad esempio, \u00e8 impossibile fare un bambino in un mese impiegando nove donne a lavorare sul compito.<br \/>\n<a name=\"esempio\"><\/a><\/p>\n<h2>Esempio di sforzo e durata del progetto<\/h2>\n<p><strong>\u00a0<\/strong>Prendiamo in considerazione, come esempio, una piccola attivit\u00e0 di pittura di un\u2019abitazione.<\/p>\n<p><em>Presupposti e stime<\/em><\/p>\n<p><em>\u00a0<\/em>1 giorno lavorativo = 8 ore di lavoro. Significa che il\/i pittore\/i lavorer\u00e0 8 ore al giorno.<\/p>\n<ul>\n<li>L&#8217;attivit\u00e0 ha una stima della durata di 4 giorni lavorativi con solo 1 pittore che lavora.<\/li>\n<li>Ci sono molti pittori disponibili per eseguire l\u2019attivit\u00e0 e tutti i pittori hanno uguale produttivit\u00e0. La quantit\u00e0 e la qualit\u00e0 del lavoro sarebbe quindi la stessa per ogni pittore.<\/li>\n<\/ul>\n<p><a name=\"durata\"><\/a><\/p>\n<h3><em>Durata<\/em><\/h3>\n<p>Se 1 pittore lavora, la durata dell&#8217;attivit\u00e0 sar\u00e0 di 4 giorni lavorativi o 32 ore lavorative.<\/p>\n<p>Se 2 pittori lavorano, la durata dell&#8217;attivit\u00e0 sar\u00e0 di 2 giorni lavorativi o 16 ore lavorative.<\/p>\n<p>Se 4 pittori lavorano, la durata dell&#8217;attivit\u00e0 sar\u00e0 di un giorno lavorativo o 8 ore lavorative.<br \/>\n<a name=\"effort\"><\/a><\/p>\n<h3><em>Effort<\/em><\/h3>\n<p>Se 1 pittore lavora, lo sforzo per l&#8217;attivit\u00e0 sar\u00e0 di 4 giorni\/persona o 32 ore\/persona.<\/p>\n<p>Se 2 pittori lavorano, lo sforzo per l&#8217;attivit\u00e0 sar\u00e0 ancora di 4 giorni\/persona o 32 ore\/persona.<\/p>\n<p>Se 4 pittori lavorano, lo sforzo sar\u00e0 sempre uguale ai casi precedenti, 4 giorni\/persona o 32 ore\/persona.<br \/>\n<a name=\"sforzo\"><\/a><\/p>\n<h3><em>Relazione tra sforzo del progetto e durata<\/em><\/h3>\n<p>La relazione tra l\u2019effort del progetto e la sua durata pu\u00f2 essere meglio espressa seguendo la seguente formula:<\/p>\n<p>Effort = Durata * Numero di risorse<\/p>\n<p><img loading=\"lazy\" decoding=\"async\" class=\"aligncenter size-full wp-image-14045\" src=\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort.png\" alt=\"effort\" width=\"1200\" height=\"799\" srcset=\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort.png 1200w, https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-630x419.png 630w, https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-1130x752.png 1130w, https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-705x469.png 705w, https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-450x300.png 450w\" sizes=\"auto, (max-width: 709px) 85vw, (max-width: 909px) 67vw, (max-width: 1362px) 62vw, 840px\" \/><\/p>\n<p>Questa formula non funzioner\u00e0 in tutti i casi, ma d\u00e0 una buona idea della relazione tra effort e durata di un progetto.<\/p>\n<p>La formula funzioner\u00e0 solo se:<\/p>\n<ul>\n<li>Il lavoro pu\u00f2 essere facilmente distribuito tra molte risorse.<\/li>\n<li>Non c&#8217;\u00e8 dipendenza tra le risorse.<\/li>\n<li>La produttivit\u00e0 di tutte le risorse \u00e8 considerata uguale.<\/li>\n<\/ul>\n<p><a name=\"conclusioni\"><\/a><\/p>\n<h2>Conclusioni<\/h2>\n<p>Quando si lavora ad un progetto con una scadenza, capire e rintracciare la <strong>differenza tra durata ed effort<\/strong> consentir\u00e0 al project manager di pianificare il tempo da dedicare a tutte le attivit\u00e0 e di rispettare la deadline.<\/p>\n<p>Inoltre, solo quando effort e durata del progetto saranno stimati, sar\u00e0 possibile per il project manager <strong>creare la stima dei costi<\/strong>.<\/p>\n<p><strong>Effort e durata<\/strong> diventano quindi due elementi chiave per la <strong>programmazione di un progetto<\/strong>.<\/p>\n<div class=\"tw_promobox box_type2 sOrange sFilter sImage\" style=\"background-image: url('https:\/\/cdn.twproject.com\/blog\/wp-content\/uploads\/picjumbo.com_HNCK5096-860.jpg');\">\n<div class=\"av_promobox avia-button-yes avia-builder-el-1 el_after_av_promobox avia-builder-el-last\">\n<div class=\"avia-promocontent\">\n<h2>Pianifica i tuoi progetti con Twproject<\/h2>\n<\/div>\n<div class=\"avia-button-wrap avia-button-right \"><a class=\"avia-button avia-icon_select-no avia-color-custom avia-size-xlarge\" href=\"https:\/\/demo.twproject.com\/applications\/teamwork\/welcome\/createUserEnvironment.jsp\" target=\"blank\"><span class=\"avia_iconbox_title\">Provalo Gratis<\/span><\/a><\/div>\n<div class=\"avia-promofooter\">Una prova \u00e8 meglio di mille parole.<\/div>\n<\/div>\n<\/div>\n","protected":false},"excerpt":{"rendered":"<p>La stima dell\u2019effort e della durata del progetto \u00e8 una funzione chiave di qualsiasi pianificazione di progetto. INDICE DEI CONTENUTI Cosa significa effort? Non solo Effort ma anche il fattore tempo Cosa significa durata? La relazione fra effort e durata Esempio di sforzo e durata del progetto Durata Effort Relazione tra sforzo del progetto e &hellip; <a href=\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\" class=\"more-link\">Leggi tutto<span class=\"screen-reader-text\"> &#8220;Effort e durata: differenza e priorit\u00e0&#8221;<\/span><\/a><\/p>\n","protected":false},"author":3,"featured_media":14046,"comment_status":"open","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_custom_body_class":"","_custom_post_class":"","footnotes":""},"categories":[224],"tags":[],"class_list":["post-14035","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-gestione-progetti-it"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v26.1 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Effort e durata: differenza e priorit\u00e0 - Twproject Blog<\/title>\n<meta name=\"description\" content=\"La stima dell\u2019effort e della durata del progetto \u00e8 una funzione chiave di qualsiasi pianificazione che permetta di portare a termine il progetto nei tempi.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\" \/>\n<meta property=\"og:locale\" content=\"it_IT\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Effort e durata: differenza e priorit\u00e0 - Twproject Blog\" \/>\n<meta property=\"og:description\" content=\"La stima dell\u2019effort e della durata del progetto \u00e8 una funzione chiave di qualsiasi pianificazione che permetta di portare a termine il progetto nei tempi.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\" \/>\n<meta property=\"og:site_name\" content=\"Twproject Blog\" \/>\n<meta property=\"article:published_time\" content=\"2020-11-11T07:00:12+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2020-11-11T23:00:03+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1245\" \/>\n\t<meta property=\"og:image:height\" content=\"800\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Twproject Staff\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Scritto da\" \/>\n\t<meta name=\"twitter:data1\" content=\"Twproject Staff\" \/>\n\t<meta name=\"twitter:label2\" content=\"Tempo di lettura stimato\" \/>\n\t<meta name=\"twitter:data2\" content=\"5 minuti\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\"},\"author\":{\"name\":\"Twproject Staff\",\"@id\":\"https:\/\/twproject.com\/blog\/#\/schema\/person\/a4b4732109ae58bf2062b8ada1d36608\"},\"headline\":\"Effort e durata: differenza e priorit\u00e0\",\"datePublished\":\"2020-11-11T07:00:12+00:00\",\"dateModified\":\"2020-11-11T23:00:03+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\"},\"wordCount\":956,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\/\/twproject.com\/blog\/#organization\"},\"image\":{\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png\",\"articleSection\":[\"Gestione Progetti\"],\"inLanguage\":\"it-IT\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\",\"url\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\",\"name\":\"Effort e durata: differenza e priorit\u00e0 - Twproject Blog\",\"isPartOf\":{\"@id\":\"https:\/\/twproject.com\/blog\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png\",\"datePublished\":\"2020-11-11T07:00:12+00:00\",\"dateModified\":\"2020-11-11T23:00:03+00:00\",\"description\":\"La stima dell\u2019effort e della durata del progetto \u00e8 una funzione chiave di qualsiasi pianificazione che permetta di portare a termine il progetto nei tempi.\",\"breadcrumb\":{\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#breadcrumb\"},\"inLanguage\":\"it-IT\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"it-IT\",\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage\",\"url\":\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png\",\"contentUrl\":\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png\",\"width\":1245,\"height\":800,\"caption\":\"effort e durata\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/twproject.com\/blog\/it\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Effort e durata: differenza e priorit\u00e0\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/twproject.com\/blog\/#website\",\"url\":\"https:\/\/twproject.com\/blog\/\",\"name\":\"Twproject Blog\",\"description\":\"Project management trends and insights. Latest Twproject news\",\"publisher\":{\"@id\":\"https:\/\/twproject.com\/blog\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/twproject.com\/blog\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"it-IT\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/twproject.com\/blog\/#organization\",\"name\":\"Twproject - Project Management Software\",\"url\":\"https:\/\/twproject.com\/blog\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"it-IT\",\"@id\":\"https:\/\/twproject.com\/blog\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/twroject-logo-m.png\",\"contentUrl\":\"https:\/\/twproject.com\/blog\/wp-content\/uploads\/twroject-logo-m.png\",\"width\":331,\"height\":110,\"caption\":\"Twproject - Project Management Software\"},\"image\":{\"@id\":\"https:\/\/twproject.com\/blog\/#\/schema\/logo\/image\/\"}},{\"@type\":\"Person\",\"@id\":\"https:\/\/twproject.com\/blog\/#\/schema\/person\/a4b4732109ae58bf2062b8ada1d36608\",\"name\":\"Twproject Staff\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"it-IT\",\"@id\":\"https:\/\/twproject.com\/blog\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/728424669417891b94e17609737aa40230ec49ae6a8fe879ca8f6c0d014f6478?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/728424669417891b94e17609737aa40230ec49ae6a8fe879ca8f6c0d014f6478?s=96&d=mm&r=g\",\"caption\":\"Twproject Staff\"},\"sameAs\":[\"twadmin\"]}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Effort e durata: differenza e priorit\u00e0 - Twproject Blog","description":"La stima dell\u2019effort e della durata del progetto \u00e8 una funzione chiave di qualsiasi pianificazione che permetta di portare a termine il progetto nei tempi.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/","og_locale":"it_IT","og_type":"article","og_title":"Effort e durata: differenza e priorit\u00e0 - Twproject Blog","og_description":"La stima dell\u2019effort e della durata del progetto \u00e8 una funzione chiave di qualsiasi pianificazione che permetta di portare a termine il progetto nei tempi.","og_url":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/","og_site_name":"Twproject Blog","article_published_time":"2020-11-11T07:00:12+00:00","article_modified_time":"2020-11-11T23:00:03+00:00","og_image":[{"width":1245,"height":800,"url":"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png","type":"image\/png"}],"author":"Twproject Staff","twitter_card":"summary_large_image","twitter_misc":{"Scritto da":"Twproject Staff","Tempo di lettura stimato":"5 minuti"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#article","isPartOf":{"@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/"},"author":{"name":"Twproject Staff","@id":"https:\/\/twproject.com\/blog\/#\/schema\/person\/a4b4732109ae58bf2062b8ada1d36608"},"headline":"Effort e durata: differenza e priorit\u00e0","datePublished":"2020-11-11T07:00:12+00:00","dateModified":"2020-11-11T23:00:03+00:00","mainEntityOfPage":{"@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/"},"wordCount":956,"commentCount":0,"publisher":{"@id":"https:\/\/twproject.com\/blog\/#organization"},"image":{"@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage"},"thumbnailUrl":"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png","articleSection":["Gestione Progetti"],"inLanguage":"it-IT","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/","url":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/","name":"Effort e durata: differenza e priorit\u00e0 - Twproject Blog","isPartOf":{"@id":"https:\/\/twproject.com\/blog\/#website"},"primaryImageOfPage":{"@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage"},"image":{"@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage"},"thumbnailUrl":"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png","datePublished":"2020-11-11T07:00:12+00:00","dateModified":"2020-11-11T23:00:03+00:00","description":"La stima dell\u2019effort e della durata del progetto \u00e8 una funzione chiave di qualsiasi pianificazione che permetta di portare a termine il progetto nei tempi.","breadcrumb":{"@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#breadcrumb"},"inLanguage":"it-IT","potentialAction":[{"@type":"ReadAction","target":["https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/"]}]},{"@type":"ImageObject","inLanguage":"it-IT","@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#primaryimage","url":"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png","contentUrl":"https:\/\/twproject.com\/blog\/wp-content\/uploads\/effort-e-durata.png","width":1245,"height":800,"caption":"effort e durata"},{"@type":"BreadcrumbList","@id":"https:\/\/twproject.com\/blog\/it\/effort-e-durata-differenza-e-priorita\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/twproject.com\/blog\/it\/"},{"@type":"ListItem","position":2,"name":"Effort e durata: differenza e priorit\u00e0"}]},{"@type":"WebSite","@id":"https:\/\/twproject.com\/blog\/#website","url":"https:\/\/twproject.com\/blog\/","name":"Twproject Blog","description":"Project management trends and insights. Latest Twproject news","publisher":{"@id":"https:\/\/twproject.com\/blog\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/twproject.com\/blog\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"it-IT"},{"@type":"Organization","@id":"https:\/\/twproject.com\/blog\/#organization","name":"Twproject - Project Management Software","url":"https:\/\/twproject.com\/blog\/","logo":{"@type":"ImageObject","inLanguage":"it-IT","@id":"https:\/\/twproject.com\/blog\/#\/schema\/logo\/image\/","url":"https:\/\/twproject.com\/blog\/wp-content\/uploads\/twroject-logo-m.png","contentUrl":"https:\/\/twproject.com\/blog\/wp-content\/uploads\/twroject-logo-m.png","width":331,"height":110,"caption":"Twproject - Project Management Software"},"image":{"@id":"https:\/\/twproject.com\/blog\/#\/schema\/logo\/image\/"}},{"@type":"Person","@id":"https:\/\/twproject.com\/blog\/#\/schema\/person\/a4b4732109ae58bf2062b8ada1d36608","name":"Twproject Staff","image":{"@type":"ImageObject","inLanguage":"it-IT","@id":"https:\/\/twproject.com\/blog\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/728424669417891b94e17609737aa40230ec49ae6a8fe879ca8f6c0d014f6478?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/728424669417891b94e17609737aa40230ec49ae6a8fe879ca8f6c0d014f6478?s=96&d=mm&r=g","caption":"Twproject Staff"},"sameAs":["twadmin"]}]}},"_links":{"self":[{"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/posts\/14035","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/users\/3"}],"replies":[{"embeddable":true,"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/comments?post=14035"}],"version-history":[{"count":2,"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/posts\/14035\/revisions"}],"predecessor-version":[{"id":14075,"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/posts\/14035\/revisions\/14075"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/media\/14046"}],"wp:attachment":[{"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/media?parent=14035"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/categories?post=14035"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/twproject.com\/blog\/it\/wp-json\/wp\/v2\/tags?post=14035"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}